*Concrete:-
·
Concrete is a mixture of binding material such as lime
or cement, well graded coarse & fine aggregate, water and some admixture.
Physical
properties of concrete:-
*Elastic
modulus of concrete:
·
It varies from 14*10³ N/mm² to 40*10³ N/mm² & increases with density and
to some extent with age.
·
Ec
= 5700 √fck N/mm², Min. grade =M15 (IS 456:1978)
·
Ec = 5000 √fck N/mm², Min. grade =M20 (IS 456:2000)
*Poisson’s
Ratio:
·
µconcrete = 0.1 to 0.3
·
For dynamic tests its value is slightly high (0.24).
·
The weight of the normal weight concrete is 2300 kg/m³ to 2600 kg/m³.
·
The
weight of plain cement concrete is 2400 kg/m³ & for RCC are 2500 kg/m³.
·
As
per the IS: 456-1978, the concrete mixes are designed into 7 grades.
·
As
per the IS: 456-2000, the concrete mixes are designed into 8 grades.
*Stages of manufacturing of
concrete:-
I.
Batching
II.
Mixing
III.
Transporting
IV.
Placing
V.
Compacting
VI.
Finishing
VII.
Curing
1. Batching:-
·
Aggregate
cement & water measured with accuracy 0f ±3% of batch quantity.
2. Mixing:-
·
Approximate
mixing time as per IS-456:1978 is 2 minutes.
·
Generally
20 revolution of concrete in mixture provides sufficient mixing.
·
Concrete mixers are specified by volume of mixed
concrete discharged after mixing of each batch expressed in m³.
·
Sometimes mixes are specified by two quantities, the
total volume of ingredients added & the volume of concrete produced for
eg.370/310.
·
10% extra cement is added in hand mixing.
·
Tilting mixers are used for large construction works.
·
Non-tilting mixers are used for small works.
·
Non-tilting mixers cannot be used when aggregate size
is more than 75 mm.
3. Transportation:-
·
A belt conveyer is used when the concrete is to be
transported continuously & to an inaccessible area.
·
Concrete pumps are commonly used on tunnel works.
·
Best method for transportation of concrete is pumping.
·
For pumping method, the compaction factor of concrete
should be 0.90 to 0.92.
·
Diameter of pipe for pumping method is 100 to 200 mm.
·
By pumping method, concrete can be transported 400 m
in horizontal & 80 m in vertical direction.
4. Placing:-
·
Delayed placing of concrete results in a gain in
ultimate compressive strength provided the concrete is adequately compacted.
·
As per IS: 456, Maximum permissible free fall concrete
may be taken as 1.5 m.
·
Placing of concrete underwater is done by tremie pipe. (Slump 150-200 mm)
5. Compaction:-
·
Process of removal of entrapped air & of uniform
placement of concrete to form a homogenous dense mass is called compaction.
·
Presence of even 5% & 10% voids in Hardened
Concrete left due to incomplete compaction may result in a decrease in
compressive strength by about 30% & 60% respectively.
·
Surface vibrators/Screed board Vibrators are used for
Road surface, plain concrete floors pavement etc. it is effective only if depth
is up to 15-20 cm.
·
External Vibrators used only when the section is thin
& heavily reinforced where penetration of needle vibrator is not possible.
·
Internal Vibrators are very effective for mass
concreting.
6. Finishing:-
·
Leveling or smoothing of top surface of freshly placed
concrete. It is done by screeding, Floating & Trowelling.
·
Screeding: The process
of removing of extra particles from the surface of concrete is known as
screeding.
·
Floating: It
consists of removing the irregularities on the surface of concrete & it is
generally done by wooden float.
·
Trowelling: It is final operation of finishing & it gives a
very smooth finish.
7. Curing:-
·
As per IS: 456, curing is the process of preventing
the loss of moisture from the concrete while maintaining a satisfactory
temperature regime.
·
The test sample should be stored in a place free from
vibration, in moist air of at least 90% relative humidity & at a Temp. Of
27°-29°C for 24 hours ± (1/2) hour from time of addition of
water to dry ingredients.
·
Curing period for rapid hardening cement is 3 to 7
days & seven days for OPC.
·
Combined water: It is chemically
combined with hydration products and it is non-evaporable.
·
Capillary
water: It partially occupied the capillary pores that constitute the
space in the cement paste remaining offer accounting for the volumes of cement
gel & unhydrated cement. It is easily evaporated.
·
Gel water: It held physically or absorbed on the surface area of
cement.
Method of Curing |
Suitability |
Shading of concrete work/ Stagnating water |
For large concrete surface such as road slab. |
Gunny bags |
For Structural concrete |
Sprinkling of water |
For vertical surfaces. |
Membranes curing |
At place of scarcity of water |
Steam (accelerated) curing |
For Precast concrete work |
*Special Points:
·
Steam curing is not suitable for high alumina cement.
·
Membrane curing is used for hilly areas.
·
Steam curing increased ultimate strength & reduced
the shear strength of concrete.
·
Concrete heated by steam at 93°C either at low or high pressure.
·
More rapid gain of strength can be obtained by with
the help of infrared radiation than steam curing.
Post a Comment